| Action Date | Action Description | 
|---|---|
| Aug 10, 2007 | Assent Application Received | 
| Aug 14, 2007 | Administrative Review for Completeness | 
| Aug 14, 2007 | Team Review for Completeness | 
| Aug 14, 2007 | Team Review for Completeness | 
| Aug 14, 2007 | Application Accepted | 
| Aug 14, 2007 | Category B assigned | 
| Aug 17, 2007 | 30 day Public Notice Issued | 
| Aug 24, 2007 | HPHC Historical Preservation No Effect | 
| Sep 16, 2007 | Public Notice End Date | 
| Jan 29, 2008 | Plans Received | 
| Feb 01, 2008 | Plans Received | 
| Mar 11, 2008 | Plans Received | 
| Mar 28, 2008 | Plans Received | 
| Mar 28, 2008 | Biologist Report | 
| Mar 28, 2008 | Engineering Report | 
| Apr 03, 2008 | Supervisor Biologist SignOff | 
| Apr 04, 2008 | Supervisor Engineer SignOff | 
| Apr 08, 2008 | Executive Signoff of Staff Reports | 
| May 02, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| May 02, 2008 | Mail Agenda Notice | 
| May 13, 2008 | Continued Application by the Council | 
| May 13, 2008 | Semi-Monthly Meeting Date Scheduled | 
| May 19, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| May 19, 2008 | Mail Agenda Notice | 
| May 27, 2008 | Semi-Monthly Meeting Held | 
| May 27, 2008 | Council Approval Granted | 
| May 27, 2008 | Semi-Monthly Meeting Date Scheduled | 
| May 28, 2008 | Stipulation Package from Biologist | 
| May 28, 2008 | Stipulation Package by Engineer | 
| May 28, 2008 | Typist for Processing | 
| May 28, 2008 | Executive Sign Off | 
| May 28, 2008 | Sent to Photo Copy | 
| May 28, 2008 | Permit Approved | 
| Aug 04, 2009 | Legal Response/Decision |