| Action Date | Action Description | 
|---|---|
| Dec 24, 2007 | Assent Application Received | 
| Dec 26, 2007 | Administrative Review for Completeness | 
| Jan 04, 2008 | Team Review for Completeness | 
| Jan 04, 2008 | Team Review for Completeness | 
| Jan 04, 2008 | Application Accepted | 
| Jan 04, 2008 | Category A* (Docks) | 
| Jan 15, 2008 | HPHC Historical Preservation No Effect | 
| Feb 08, 2008 | Additional Information Received | 
| Mar 13, 2008 | 30 day Public Notice Issued | 
| Apr 11, 2008 | Correspondence Received | 
| Apr 13, 2008 | Public Notice End Date | 
| Apr 29, 2008 | Dock Meeting -- Approval | 
| Apr 30, 2008 | Permit Approved | 
| Apr 30, 2008 | Typist for Processing | 
| Apr 30, 2008 | Executive Sign Off | 
| Apr 30, 2008 | Sent to Photo Copy | 
| Apr 30, 2008 | Biologist Report | 
| Apr 30, 2008 | Engineering Report | 
| May 01, 2008 | US Army Corp of Engineers Permit Date | 
| May 05, 2008 | US Army Corps of Engineers Approval Received | 
| May 16, 2008 | Land Evidence Date |