| Action Date | Action Description | 
|---|---|
| Monitoring Report | |
| Jan 30, 2008 | Assent Application Received | 
| Jan 31, 2008 | Administrative Review for Completeness | 
| Feb 05, 2008 | Team Review for Completeness | 
| Feb 05, 2008 | Application Accepted | 
| Feb 07, 2008 | 30 day Public Notice Issued | 
| Feb 14, 2008 | HPHC Historical Preservation No Effect | 
| Feb 26, 2008 | Additional Information Received | 
| Mar 07, 2008 | Public Notice End Date | 
| Apr 14, 2008 | Engineering Report | 
| Apr 15, 2008 | Biologist Report | 
| Apr 21, 2008 | US Army Corp of Engineers Permit Date | 
| Apr 23, 2008 | US Army Corps of Engineers Approval Received | 
| Apr 29, 2008 | Dock/1.1.6 Review approval | 
| Apr 29, 2008 | Scheduled for Section 110 Review meeting | 
| May 05, 2008 | Typist for Processing | 
| May 05, 2008 | Executive Sign Off | 
| May 05, 2008 | Sent to Photo Copy | 
| May 05, 2008 | Permit Approved | 
| Aug 22, 2008 | Duplicate Original Assent requested/mailed | 
| Aug 27, 2008 | Land Evidence Date | 
| Nov 24, 2008 | Commencement of Work Notice received | 
| Dec 08, 2009 | Letter of Authorization | 
| Nov 18, 2010 | Monitoring Report | 
| Nov 01, 2011 | Monitoring Report |