| Action Date | Action Description | 
|---|---|
| Feb 21, 2008 | Assent Application Received | 
| Feb 22, 2008 | Administrative Review for Completeness | 
| Feb 22, 2008 | Team Review for Completeness | 
| Feb 22, 2008 | Team Review for Completeness | 
| Feb 22, 2008 | Application Accepted | 
| Mar 18, 2008 | HPHC Historical Preservation No Effect | 
| Apr 21, 2008 | Additional Information Received | 
| Apr 25, 2008 | Additional Information Received | 
| Apr 25, 2008 | Typist for Processing | 
| Apr 25, 2008 | Executive Sign Off | 
| Apr 25, 2008 | Sent to Photo Copy | 
| Apr 25, 2008 | Permit Approved | 
| Apr 25, 2008 | Biologist Report | 
| Apr 25, 2008 | Engineering Report | 
| May 02, 2008 | Land Evidence Date | 
| May 02, 2008 | Commencement of Work Notice received | 
| Jun 20, 2008 | Modification Request | 
| Jun 25, 2008 | Administrative Review for Completeness | 
| Jun 25, 2008 | Team Review for Completeness | 
| Jun 25, 2008 | Team Review for Completeness | 
| Jun 27, 2008 | Biologist Report | 
| Jun 27, 2008 | Engineering Report | 
| Jun 27, 2008 | Typist for Processing | 
| Jun 27, 2008 | Modification Approved | 
| Jul 03, 2008 | Land Evidence Date | 
| Jul 03, 2008 | Executive Sign Off | 
| Jul 03, 2008 | Sent to Photo Copy |