| Action Date | Action Description | 
|---|---|
| Legal Response/Decision | |
| Apr 07, 2008 | Assent Application Received | 
| Apr 08, 2008 | Administrative Review for Completeness | 
| Apr 08, 2008 | Team Review for Completeness | 
| Apr 08, 2008 | Team Review for Completeness | 
| Apr 10, 2008 | Deficient Application - Owner Notification Sent | 
| Apr 14, 2008 | Deficient Application Picked Up | 
| Jul 01, 2008 | Deficiency Response Received | 
| Jul 01, 2008 | Administrative Review for Completeness | 
| Jul 08, 2008 | Plans Received | 
| Jul 09, 2008 | 30 day Public Notice Issued | 
| Jul 09, 2008 | Application Accepted | 
| Jul 09, 2008 | Team Review for Completeness | 
| Jul 09, 2008 | Team Review for Completeness | 
| Jul 09, 2008 | Category A* (Docks) | 
| Jul 15, 2008 | HPHC Historical Preservation No Effect | 
| Jul 28, 2008 | Objections/Comments Received | 
| Aug 09, 2008 | Public Notice End Date | 
| Sep 03, 2008 | Biologist Report | 
| Sep 03, 2008 | Engineering Report | 
| Sep 03, 2008 | Supervisor Biologist SignOff | 
| Sep 03, 2008 | Supervisor Engineer SignOff | 
| Sep 03, 2008 | Executive Signoff of Staff Reports | 
| Sep 03, 2008 | US Army Corp of Engineers Permit Date | 
| Sep 08, 2008 | US Army Corps of Engineers Approval Received | 
| Sep 15, 2008 | Mail Agenda Notice | 
| Sep 15, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Sep 18, 2008 | Correspondence Received | 
| Sep 22, 2008 | Continuance request by applicant granted by Director | 
| Sep 23, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Oct 02, 2008 | Mail Agenda Notice | 
| Oct 02, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Oct 14, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Nov 07, 2008 | Mail Agenda Notice | 
| Nov 25, 2008 | Semi-Monthly Meeting Postponed | 
| Nov 25, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Nov 25, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Nov 26, 2008 | Mail Agenda Notice | 
| Dec 01, 2008 | Entry of Appearance Received | 
| Dec 09, 2008 | Semi-Monthly Meeting Postponed | 
| Dec 09, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Dec 11, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Dec 11, 2008 | Mail Agenda Notice | 
| Dec 16, 2008 | Continuance Requested | 
| Dec 17, 2008 | Management Review | 
| Dec 22, 2008 | Correspondence Received | 
| Dec 22, 2008 | Mail Agenda Notice | 
| Jan 21, 2009 | Mail Agenda Notice | 
| Jan 27, 2009 | Semi-Monthly Meeting Held | 
| Jan 27, 2009 | Council Approval Granted | 
| Jan 27, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Jan 29, 2009 | Stipulation Package from Biologist | 
| Jan 29, 2009 | Stipulation Package by Engineer | 
| Jan 29, 2009 | Permit Approved | 
| Jan 29, 2009 | Typist for Processing | 
| Jan 29, 2009 | Executive Sign Off | 
| Jan 29, 2009 | Sent to Photo Copy | 
| Apr 20, 2009 | Land Evidence Date |