| Action Date | Action Description | 
|---|---|
| Legal Response/Decision | |
| Jul 11, 2008 | Assent Application Received | 
| Jul 14, 2008 | Administrative Review for Completeness | 
| Jul 16, 2008 | Team Review for Completeness | 
| Jul 16, 2008 | Team Review for Completeness | 
| Jul 16, 2008 | Application Accepted | 
| Jul 17, 2008 | Category B assigned | 
| Jul 28, 2008 | 30 day Public Notice Issued | 
| Jul 30, 2008 | Additional Information Received | 
| Aug 14, 2008 | HPHC Historical Preservation No Effect | 
| Aug 28, 2008 | Public Notice End Date | 
| Oct 31, 2008 | US Army Corp of Engineers Permit Date | 
| Nov 03, 2008 | US Army Corps of Engineers Approval Received | 
| Nov 05, 2008 | Plans Received | 
| Aug 24, 2009 | Plans Received | 
| Dec 08, 2009 | Engineering Report | 
| Dec 08, 2009 | Biologist Report | 
| Dec 11, 2009 | Supervisor Biologist SignOff | 
| Dec 11, 2009 | Supervisor Engineer SignOff | 
| Dec 18, 2009 | Executive Signoff of Staff Reports | 
| Jan 19, 2010 | Ready to Schedule Semi-Monthly Meeting | 
| Jan 19, 2010 | Mail Agenda Notice | 
| Jan 27, 2010 | Semi-Monthly Meeting Held | 
| Jan 27, 2010 | Council Approval Granted | 
| Jan 27, 2010 | Semi-Monthly Meeting Date Scheduled | 
| Mar 03, 2010 | Stipulation Package from Biologist | 
| Mar 03, 2010 | Stipulation Package by Engineer | 
| Mar 09, 2010 | Permit Approved | 
| Mar 23, 2010 | Permit Revoked |