| Action Date | Action Description |
|---|---|
| Enforcement Compliance Inspection Required | |
| Nov 21, 2008 | Assent Application Received |
| Nov 25, 2008 | Additional Information Requested from Applicant |
| Dec 16, 2008 | Correspondence Received |
| Dec 17, 2008 | Team Review for Completeness |
| Dec 17, 2008 | Team Review for Completeness |
| Dec 17, 2008 | Application Accepted |
| Dec 17, 2008 | Administrative Review for Completeness |
| Jan 21, 2009 | HPHC Historical Preservation No Effect |
| Apr 29, 2009 | Biologist Report |
| Apr 29, 2009 | Engineering Report |
| May 03, 2009 | Supervisor Engineer SignOff |
| May 20, 2009 | Supervisor Biologist SignOff |
| Jun 30, 2009 | Executive Signoff of Staff Reports |
| Jul 20, 2009 | Ready to Schedule Semi-Monthly Meeting |
| Jul 20, 2009 | Mail Agenda Notice |
| Jul 28, 2009 | Continued Application by the Council |
| Jul 28, 2009 | Semi-Monthly Meeting Date Scheduled |
| Oct 06, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Oct 14, 2010 | Typist for Processing |
| Oct 14, 2010 | Permit Approved |
| Oct 18, 2010 | Executive Sign Off |
| Oct 18, 2010 | Sent to Photo Copy |
| Oct 29, 2010 | Land Evidence Date |
| Sep 23, 2011 | Correspondence Received |
| Jul 01, 2014 | Extension Toll letter mailed |
| Apr 05, 2018 | Correspondence Received |
| May 01, 2018 | Extension Toll letter mailed |
| Nov 05, 2018 | Correspondence Received |
| Jun 28, 2019 | Extension of Permit Request |
| Mar 16, 2021 | Modification Request |
| Mar 16, 2021 | Administrative Review for Completeness |
| Apr 27, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Apr 27, 2021 | Process Extension |
| Apr 27, 2021 | Extension Approved |
| May 21, 2021 | Correspondence Mailed/Faxed/E-mailed |
| May 21, 2021 | Bio Team Review for Completeness |
| Sep 16, 2021 | Additional Information Received |
| May 16, 2022 | Additional Information Received |
| Aug 26, 2022 | Biologist Report |
| Aug 30, 2022 | Typist for Processing |
| Aug 30, 2022 | Executive Sign Off |
| Aug 30, 2022 | Sent to Photo Copy |
| Aug 30, 2022 | Modification Approved |
| Jan 17, 2023 | Land Evidence Date |