| Action Date | Action Description | 
|---|---|
| Nov 24, 2008 | Assent Application Received | 
| Nov 25, 2008 | Administrative Review for Completeness | 
| Nov 26, 2008 | Team Review for Completeness | 
| Nov 26, 2008 | Team Review for Completeness | 
| Nov 26, 2008 | Application Accepted | 
| Sep 28, 2010 | Additional Information Received | 
| Jun 17, 2011 | Biologist Report | 
| Jun 17, 2011 | Engineering Report | 
| Jun 21, 2011 | Typist for Processing | 
| Jun 21, 2011 | Permit Approved | 
| Jun 22, 2011 | Executive Sign Off | 
| Jun 22, 2011 | Sent to Photo Copy | 
| Jul 15, 2011 | US Army Corps of Engineers Approval Received | 
| Jul 27, 2011 | Land Evidence Date |