| Action Date | Action Description | 
|---|---|
| Apr 02, 2009 | Assent Application Received | 
| Apr 04, 2009 | Administrative Review for Completeness | 
| Apr 06, 2009 | Team Review for Completeness | 
| Apr 06, 2009 | Team Review for Completeness | 
| Apr 06, 2009 | Application Accepted | 
| Apr 09, 2009 | HPHC Historical Preservation No Effect | 
| Apr 10, 2009 | 30 day Public Notice Issued | 
| Jun 04, 2009 | Public Notice End Date | 
| Jun 05, 2009 | Correspondence Received | 
| Jun 23, 2009 | Additional Information Received | 
| Jun 26, 2009 | Dock Meeting -- Approval | 
| Jul 09, 2009 | Biologist Report | 
| Jul 09, 2009 | Engineering Report | 
| Jul 13, 2009 | US Army Corp of Engineers Permit Date | 
| Jul 14, 2009 | Typist for Processing | 
| Jul 14, 2009 | Executive Sign Off | 
| Jul 14, 2009 | Sent to Photo Copy | 
| Jul 14, 2009 | Permit Approved | 
| Jul 22, 2009 | US Army Corps of Engineers Approval Received | 
| Jul 27, 2009 | Land Evidence Date |