| Action Date | Action Description | 
|---|---|
| Oct 30, 2009 | Assent Application Received | 
| Nov 04, 2009 | Administrative Review for Completeness | 
| Nov 05, 2009 | Team Review for Completeness | 
| Nov 05, 2009 | Team Review for Completeness | 
| Nov 05, 2009 | Application Accepted | 
| Nov 13, 2009 | Biologist Report | 
| Nov 13, 2009 | Engineering Report | 
| Nov 16, 2009 | Typist for Processing | 
| Nov 16, 2009 | Executive Sign Off | 
| Nov 16, 2009 | Sent to Photo Copy | 
| Nov 16, 2009 | Permit Approved | 
| Dec 15, 2009 | Land Evidence Date |