| Action Date | Action Description | 
|---|---|
| Mar 03, 2010 | Maintenance Certification Request | 
| Mar 04, 2010 | Administrative Review for Completeness | 
| Mar 08, 2010 | Team Review for Completeness | 
| Mar 08, 2010 | Team Review for Completeness | 
| Mar 08, 2010 | Application Accepted | 
| Mar 16, 2010 | Additional Information Requested from Applicant | 
| Mar 25, 2010 | HPHC Historical Preservation No Effect | 
| Oct 05, 2010 | 30-Day Notification of Cancellation letter | 
| Oct 08, 2010 | Certified Receipt Received | 
| Oct 22, 2010 | Biologist Report | 
| Oct 25, 2010 | Permit Approved | 
| Oct 26, 2010 | Typist for Processing | 
| Oct 26, 2010 | Executive Sign Off | 
| Oct 26, 2010 | Sent to Photo Copy | 
| Nov 24, 2010 | Land Evidence Date | 
| Dec 08, 2010 | Correspondence Received | 
| Dec 09, 2010 | Correspondence Mailed/Faxed/E-mailed |