| Action Date | Action Description | 
|---|---|
| Mar 16, 2010 | Assent Application Received | 
| Mar 16, 2010 | Administrative Review for Completeness | 
| Mar 16, 2010 | Team Review for Completeness | 
| Mar 16, 2010 | Team Review for Completeness | 
| Mar 19, 2010 | Team Review for Completeness | 
| Mar 19, 2010 | Team Review for Completeness | 
| Mar 22, 2010 | Deficient Application - Owner Notification Sent | 
| Apr 30, 2010 | Deficiency Response Received | 
| May 04, 2010 | Team Review for Completeness | 
| May 04, 2010 | Team Review for Completeness | 
| May 11, 2010 | Application Accepted | 
| May 13, 2010 | 30 day Public Notice Issued | 
| May 20, 2010 | HPHC Historical Preservation No Effect | 
| Jun 02, 2010 | Objections/Comments Received | 
| Jun 13, 2010 | Public Notice End Date | 
| Jun 21, 2010 | US Army Corp of Engineers Permit Date | 
| Jun 25, 2010 | US Army Corps of Engineers Approval Received | 
| Jul 14, 2010 | Dock Meeting Scheduled (Admin) | 
| Sep 30, 2010 | Correspondence Received | 
| Apr 20, 2011 | Engineering Report | 
| Apr 21, 2011 | Biologist Report | 
| Apr 22, 2011 | Supervisor Engineer SignOff | 
| Apr 22, 2011 | Supervisor Biologist SignOff | 
| Apr 26, 2011 | Executive Signoff of Staff Reports | 
| Jun 03, 2011 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 03, 2011 | Mail Agenda Notice | 
| Jun 07, 2011 | Correspondence Received | 
| Jun 07, 2011 | Continuance Requested | 
| Jun 07, 2011 | Entry of Appearance Received | 
| Jun 08, 2011 | Continuance request by applicant granted by Director | 
| Jun 08, 2011 | Management Review | 
| Jun 14, 2011 | Semi-Monthly Meeting Date Scheduled | 
| Jun 16, 2011 | Dock Subcommittee Meeting Held | 
| Jun 16, 2011 | Dock Meeting -- Approval | 
| Jun 22, 2011 | Category A* (Docks) | 
| Jun 24, 2011 | Permit Approved | 
| Jun 24, 2011 | Typist for Processing | 
| Jun 27, 2011 | Executive Sign Off | 
| Jun 27, 2011 | Sent to Photo Copy | 
| Jul 05, 2011 | Land Evidence Date |