| Action Date | Action Description |
|---|---|
| Apr 07, 2010 | Assent Application Received |
| Apr 08, 2010 | Administrative Review for Completeness |
| Apr 08, 2010 | Team Review for Completeness |
| Apr 08, 2010 | Application Accepted |
| Apr 16, 2010 | HPHC Historical Preservation No Effect |
| May 21, 2010 | Additional Information Received |
| May 25, 2010 | 30 day Public Notice Issued |
| Jun 24, 2010 | Public Notice End Date |
| Nov 23, 2010 | Plans Received |
| Mar 07, 2011 | Additional Information Received |
| Mar 14, 2011 | Additional Information Received |
| Mar 23, 2011 | US Army Corps of Engineers Approval Received |
| Apr 06, 2011 | Dock Meeting -- Approval |
| Apr 06, 2011 | Biologist Report |
| Apr 07, 2011 | Permit Approved |
| Apr 07, 2011 | Typist for Processing |
| May 02, 2011 | Executive Sign Off |
| May 02, 2011 | Sent to Photo Copy |
| Aug 22, 2011 | Land Evidence Date |