| Action Date | Action Description | 
|---|---|
| Jun 22, 2010 | Maintenance Certification Request | 
| Jun 23, 2010 | Administrative Review for Completeness | 
| Jun 23, 2010 | Team Review for Completeness | 
| Jun 23, 2010 | Team Review for Completeness | 
| Jun 23, 2010 | Application Accepted | 
| Jun 29, 2010 | Biologist Report | 
| Jun 29, 2010 | Engineering Report | 
| Jul 01, 2010 | Typist for Processing | 
| Jul 01, 2010 | Permit Approved | 
| Jul 06, 2010 | Executive Sign Off | 
| Jul 06, 2010 | Sent to Photo Copy | 
| Jul 26, 2010 | HPHC Historical Preservation No Effect |