| Action Date | Action Description | 
|---|---|
| Aug 17, 2010 | Assent Application Received | 
| Aug 18, 2010 | Administrative Review for Completeness | 
| Aug 19, 2010 | Team Review for Completeness | 
| Aug 19, 2010 | Team Review for Completeness | 
| Aug 19, 2010 | Application Accepted | 
| Sep 09, 2010 | HPHC Historical Preservation No Effect | 
| Dec 01, 2010 | Additional Information Received | 
| Jan 21, 2011 | 30 day Public Notice Issued | 
| Jan 25, 2011 | Biologist Report | 
| Jan 26, 2011 | Engineering Report | 
| Feb 08, 2011 | Mail Agenda Notice | 
| Feb 08, 2011 | Ready to Schedule Semi-Monthly Meeting | 
| Feb 11, 2011 | Objections/Comments Received | 
| Feb 21, 2011 | Objections/Comments Received | 
| Feb 21, 2011 | Public Notice End Date | 
| Feb 22, 2011 | Continuance request by objector granted by Director | 
| Feb 22, 2011 | Semi-Monthly Meeting Date Scheduled | 
| Feb 23, 2011 | Public Hearing Notices Mailed | 
| Mar 17, 2011 | Continuance Requested | 
| Mar 18, 2011 | Continuance request by applicant granted by Council | 
| Mar 22, 2011 | Semi-Monthly Meeting Date Scheduled | 
| Mar 28, 2011 | Ready to Schedule Semi-Monthly Meeting | 
| Mar 28, 2011 | Public Hearing Notices Mailed | 
| Apr 20, 2011 | Mail Agenda Notice | 
| Apr 26, 2011 | Continued Application by the Council | 
| Apr 26, 2011 | Semi-Monthly Meeting Date Scheduled | 
| May 04, 2011 | Semi-Monthly Meeting Date Scheduled | 
| May 04, 2011 | Semi-Monthly Meeting Held | 
| May 04, 2011 | Council Approval Granted | 
| May 24, 2011 | Correspondence Received | 
| Jun 06, 2011 | Correspondence Received | 
| Jul 12, 2011 | Legal Response/Decision | 
| Jul 15, 2011 | Typist for Processing | 
| Jul 15, 2011 | Stipulation Package from Biologist | 
| Jul 15, 2011 | Stipulation Package by Engineer | 
| Jul 15, 2011 | Permit Approved | 
| Jul 19, 2011 | Executive Sign Off | 
| Jul 19, 2011 | Sent to Photo Copy | 
| Aug 02, 2011 | Land Evidence Date | 
| Jun 27, 2013 | Modification Request | 
| Jul 01, 2013 | Administrative Review for Completeness | 
| Jul 02, 2013 | Team Review for Completeness | 
| Jul 02, 2013 | Team Review for Completeness | 
| Jul 12, 2013 | Biologist Report | 
| Jul 12, 2013 | Engineering Report | 
| Jul 15, 2013 | Typist for Processing | 
| Jul 15, 2013 | Modification Approved | 
| Jul 16, 2013 | Executive Sign Off | 
| Jul 16, 2013 | Sent to Photo Copy | 
| Jul 18, 2013 | Land Evidence Date | 
| Jul 22, 2013 | HPHC Historical Preservation No Effect | 
| Nov 17, 2020 | Letter of Authorization | 
| Jul 15, 2061 | Assent Expiration Date |