| Action Date | Action Description | 
|---|---|
| Oct 01, 2010 | Assent Application Received | 
| Oct 01, 2010 | Administrative Review for Completeness | 
| Oct 13, 2010 | Team Review for Completeness | 
| Oct 13, 2010 | Team Review for Completeness | 
| Oct 13, 2010 | Application Accepted | 
| Oct 20, 2010 | HPHC Historical Preservation No Effect | 
| Nov 15, 2010 | 30 day Public Notice Issued | 
| Dec 15, 2010 | Public Notice End Date | 
| Feb 18, 2011 | Additional Information Received | 
| Mar 01, 2011 | US Army Corps of Engineers Approval Received | 
| Mar 11, 2011 | Additional Information Received | 
| Mar 18, 2011 | Correspondence Received | 
| Mar 18, 2011 | Correspondence Received | 
| Apr 07, 2011 | Biologist Report | 
| Apr 07, 2011 | Engineering Report | 
| Apr 12, 2011 | Typist for Processing | 
| Apr 12, 2011 | Executive Sign Off | 
| Apr 12, 2011 | Sent to Photo Copy | 
| Apr 12, 2011 | Permit Approved | 
| Apr 29, 2011 | Land Evidence Date | 
| Jun 06, 2011 | Commencement of Work Notice received |