| Action Date | Action Description | 
|---|---|
| Nov 16, 2010 | Assent Application Received | 
| Nov 16, 2010 | Administrative Review for Completeness | 
| Nov 17, 2010 | Team Review for Completeness | 
| Nov 17, 2010 | Team Review for Completeness | 
| Nov 17, 2010 | Application Accepted | 
| Nov 17, 2010 | Category A* (Docks) | 
| Dec 02, 2010 | HPHC Historical Preservation No Effect | 
| Dec 03, 2010 | Additional Information Received | 
| Dec 06, 2010 | Additional Information Received | 
| Dec 10, 2010 | Additional Information Received | 
| Dec 13, 2010 | 30 day Public Notice Issued | 
| Jan 13, 2011 | Public Notice End Date | 
| Jan 14, 2011 | Dock Meeting Scheduled (Admin) | 
| Jan 21, 2011 | Biologist Report | 
| Jan 21, 2011 | Engineering Report | 
| Jan 25, 2011 | Typist for Processing | 
| Jan 25, 2011 | Executive Sign Off | 
| Jan 25, 2011 | Sent to Photo Copy | 
| Jan 25, 2011 | Permit Approved | 
| Feb 07, 2011 | US Army Corps of Engineers Approval Received | 
| Feb 10, 2011 | Land Evidence Date | 
| May 12, 2011 | Commencement of Work Notice received |