| Action Date | Action Description | 
|---|---|
| Jan 21, 2011 | Federal Consistency Review Request | 
| Jan 24, 2011 | Administrative Review for Completeness | 
| Jan 24, 2011 | Team Review for Completeness | 
| Jan 24, 2011 | Application Accepted | 
| Mar 31, 2011 | Additional Information Requested from Applicant | 
| May 16, 2011 | Correspondence Received | 
| Sep 01, 2011 | HPHC Historical Preservation Comments/Concerns | 
| Sep 27, 2011 | Additional Information Requested from Applicant | 
| Dec 19, 2011 | HPHC Historical Preservation Comments/Concerns | 
| Apr 16, 2012 | Additional Information Received | 
| Aug 28, 2012 | Historical Preservation Conditional Approval | 
| Dec 21, 2012 | Correspondence Received | 
| Dec 21, 2012 | Correspondence Received | 
| Dec 24, 2012 | Correspondence Received | 
| Dec 27, 2012 | Correspondence Received | 
| Feb 19, 2013 | Mail Agenda Notice | 
| Feb 21, 2013 | Engineering Report | 
| Feb 28, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Mar 26, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Mar 28, 2013 | Federal Consistency FMP Concurrence |