| Action Date | Action Description | 
|---|---|
| Feb 11, 2011 | Assent Application Received | 
| Feb 14, 2011 | Administrative Review for Completeness | 
| Feb 14, 2011 | Team Review for Completeness | 
| Feb 14, 2011 | Team Review for Completeness | 
| Feb 14, 2011 | Application Accepted | 
| Feb 15, 2011 | Additional Information Received | 
| Mar 17, 2011 | HPHC Historical Preservation No Effect | 
| Mar 23, 2011 | Additional Information Received | 
| Jul 01, 2011 | Additional Information Received | 
| Aug 18, 2011 | Additional Information Received | 
| Aug 18, 2011 | Biologist Report | 
| Aug 18, 2011 | Engineering Report | 
| Aug 23, 2011 | Typist for Processing | 
| Aug 23, 2011 | Permit Approved | 
| Aug 25, 2011 | Executive Sign Off | 
| Aug 25, 2011 | Sent to Photo Copy | 
| Aug 31, 2011 | Land Evidence Date | 
| Oct 24, 2011 | Commencement of Work Notice received | 
| Feb 08, 2012 | Modification Request | 
| Feb 08, 2012 | Administrative Review for Completeness | 
| Feb 09, 2012 | Team Review for Completeness | 
| Feb 09, 2012 | Team Review for Completeness | 
| Feb 15, 2012 | Biologist Report | 
| Feb 15, 2012 | Engineering Report | 
| Feb 17, 2012 | Typist for Processing | 
| Feb 17, 2012 | Executive Sign Off | 
| Feb 17, 2012 | Sent to Photo Copy | 
| Feb 17, 2012 | Modification Approved | 
| Feb 27, 2012 | Land Evidence Date | 
| Mar 06, 2012 | HPHC Historical Preservation No Effect |