| Action Date | Action Description | 
|---|---|
| Mar 07, 2011 | Assent Application Received | 
| Mar 08, 2011 | Administrative Review for Completeness | 
| Mar 08, 2011 | Team Review for Completeness | 
| Mar 08, 2011 | Application Accepted | 
| Mar 08, 2011 | Category B assigned | 
| Mar 15, 2011 | 30 day Public Notice Issued | 
| Mar 25, 2011 | HPHC Historical Preservation No Effect | 
| Apr 13, 2011 | Public Notice End Date | 
| Apr 19, 2011 | US Army Corps of Engineers Approval Received | 
| Apr 26, 2011 | Permit Approved | 
| Apr 26, 2011 | Category M assigned | 
| Apr 26, 2011 | Typist for Processing | 
| Apr 26, 2011 | Engineering Report | 
| Apr 27, 2011 | Executive Sign Off | 
| Apr 27, 2011 | Sent to Photo Copy | 
| Jul 19, 2011 | Land Evidence Date | 
| Apr 11, 2014 | Modification Request | 
| Jun 13, 2014 | 30 day Public Notice Issued | 
| Jul 13, 2014 | Public Notice End Date | 
| Jul 22, 2014 | Engineering Report | 
| Jul 23, 2014 | Typist for Processing | 
| Jul 23, 2014 | Modification Approved | 
| Jul 25, 2014 | Executive Sign Off | 
| Jul 25, 2014 | Sent to Photo Copy | 
| Jul 29, 2014 | Land Evidence Date | 
| Jul 31, 2014 | US Army Corps of Engineers Approval Received |