| Action Date | Action Description | 
|---|---|
| Nov 01, 2011 | Assent Application Received | 
| Nov 02, 2011 | Administrative Review for Completeness | 
| Nov 04, 2011 | Team Review for Completeness | 
| Nov 04, 2011 | Team Review for Completeness | 
| Nov 04, 2011 | Category A assigned | 
| Nov 04, 2011 | Engineering Report | 
| Nov 08, 2011 | Permit Approved | 
| Nov 08, 2011 | Typist for Processing | 
| Nov 09, 2011 | Executive Sign Off | 
| Nov 09, 2011 | Sent to Photo Copy | 
| Nov 21, 2011 | Land Evidence Date |