| Action Date | Action Description | 
|---|---|
| Feb 16, 2012 | Assent Application Received | 
| Feb 17, 2012 | Administrative Review for Completeness | 
| Feb 17, 2012 | Team Review for Completeness | 
| Feb 17, 2012 | Team Review for Completeness | 
| Feb 17, 2012 | Application Accepted | 
| Feb 17, 2012 | Category B assigned | 
| Feb 23, 2012 | 30 day Public Notice Issued | 
| Feb 28, 2012 | HPHC Historical Preservation No Effect | 
| Mar 24, 2012 | Public Notice End Date | 
| Apr 09, 2012 | US Army Corps of Engineers Approval Received | 
| May 25, 2012 | Additional Information Received | 
| May 31, 2012 | Biologist Report | 
| May 31, 2012 | Engineering Report | 
| Jun 06, 2012 | Supervisor Biologist SignOff | 
| Jun 06, 2012 | Supervisor Engineer SignOff | 
| Jun 06, 2012 | Executive Signoff of Staff Reports | 
| Jun 18, 2012 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 18, 2012 | Mail Agenda Notice | 
| Jun 26, 2012 | Council Approval Granted | 
| Jun 26, 2012 | Semi-Monthly Meeting Date Scheduled | 
| Jun 26, 2012 | Semi-Monthly Meeting Held | 
| Jun 28, 2012 | Stipulation Package from Biologist | 
| Jun 28, 2012 | Stipulation Package by Engineer | 
| Jun 29, 2012 | Legal Response/Decision | 
| Jun 29, 2012 | 30 Day Appeal Notification to Owner | 
| Jul 02, 2012 | Permit Approved | 
| Jul 02, 2012 | Typist for Processing | 
| Jul 03, 2012 | Executive Sign Off | 
| Jul 03, 2012 | Sent to Photo Copy | 
| Jul 20, 2012 | Land Evidence Date | 
| Oct 01, 2012 | Modification Request | 
| Oct 02, 2012 | Administrative Review for Completeness | 
| Oct 02, 2012 | Team Review for Completeness | 
| Oct 02, 2012 | Team Review for Completeness | 
| Oct 03, 2012 | Biologist Report | 
| Oct 03, 2012 | Engineering Report | 
| Oct 03, 2012 | Typist for Processing | 
| Oct 03, 2012 | Modification Approved | 
| Oct 09, 2012 | Executive Sign Off | 
| Oct 09, 2012 | Sent to Photo Copy | 
| Oct 10, 2012 | HPHC Historical Preservation No Effect | 
| Oct 19, 2012 | Land Evidence Date |