| Action Date | Action Description | 
|---|---|
| Mar 05, 2012 | Maintenance Certification Request | 
| Mar 05, 2012 | Administrative Review for Completeness | 
| Mar 06, 2012 | Team Review for Completeness | 
| Mar 06, 2012 | Team Review for Completeness | 
| Mar 06, 2012 | Application Accepted | 
| Mar 12, 2012 | Biologist Report | 
| Mar 12, 2012 | Engineering Report | 
| Mar 14, 2012 | Typist for Processing | 
| Mar 14, 2012 | Permit Approved | 
| Mar 15, 2012 | Executive Sign Off | 
| Mar 15, 2012 | Sent to Photo Copy | 
| Mar 21, 2012 | Land Evidence Date | 
| Apr 03, 2012 | HPHC Historical Preservation No Effect |