| Action Date | Action Description | 
|---|---|
| May 03, 2012 | Assent Application Received | 
| May 03, 2012 | Administrative Review for Completeness | 
| May 04, 2012 | Team Review for Completeness | 
| May 04, 2012 | Team Review for Completeness | 
| May 04, 2012 | Application Accepted | 
| May 16, 2012 | Additional Information Received | 
| May 21, 2012 | Biologist Report | 
| May 21, 2012 | Engineering Report | 
| May 25, 2012 | Typist for Processing | 
| May 25, 2012 | Permit Approved | 
| May 29, 2012 | Executive Sign Off | 
| May 29, 2012 | Sent to Photo Copy | 
| Jun 01, 2012 | Land Evidence Date | 
| Nov 01, 2012 | HPHC Historical Preservation No Effect |