| Action Date | Action Description | 
|---|---|
| Jul 25, 2012 | Assent Application Received | 
| Jul 26, 2012 | Administrative Review for Completeness | 
| Aug 01, 2012 | Team Review for Completeness | 
| Aug 01, 2012 | Team Review for Completeness | 
| Aug 01, 2012 | Application Accepted | 
| Aug 07, 2012 | Additional Information Requested from Applicant | 
| Aug 07, 2012 | 30-Day Notification of Cancellation letter | 
| Sep 01, 2012 | HPHC Historical Preservation No Effect | 
| Sep 11, 2012 | Additional Information Received | 
| Oct 01, 2012 | 30 day Public Notice Issued | 
| Oct 19, 2012 | Objections/Comments Received | 
| Nov 01, 2012 | Additional Information Received | 
| Nov 01, 2012 | Correspondence Received | 
| Nov 01, 2012 | Public Notice End Date | 
| Dec 27, 2012 | Additional Information Received | 
| Jan 15, 2013 | US Army Corp of Engineers Permit Date | 
| Feb 05, 2013 | Engineering Report | 
| Feb 05, 2013 | Supervisor Biologist SignOff | 
| Feb 05, 2013 | Supervisor Engineer SignOff | 
| Feb 05, 2013 | Biologist Report | 
| Feb 06, 2013 | Executive Signoff of Staff Reports | 
| Mar 05, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Mar 05, 2013 | Mail Agenda Notice | 
| Mar 12, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Mar 14, 2013 | Mail Agenda Notice | 
| Mar 26, 2013 | Council Approval Granted | 
| Mar 26, 2013 | Semi-Monthly Meeting Held | 
| Mar 26, 2013 | Semi-Monthly Meeting Date Scheduled | 
| May 07, 2013 | Legal Response/Decision | 
| May 07, 2013 | 30 Day Appeal Notification to Owner | 
| Jun 25, 2013 | Stipulation Package from Biologist | 
| Jun 25, 2013 | Stipulation Package by Engineer | 
| Jul 08, 2013 | Typist for Processing | 
| Jul 08, 2013 | Permit Approved | 
| Jul 09, 2013 | Executive Sign Off | 
| Jul 09, 2013 | Sent to Photo Copy | 
| Jul 30, 2013 | Land Evidence Date |