| Action Date | Action Description |
|---|---|
| Dec 13, 2012 | Assent Application Received |
| Dec 14, 2012 | Administrative Review for Completeness |
| Dec 26, 2012 | Team Review for Completeness |
| Dec 26, 2012 | Team Review for Completeness |
| Dec 26, 2012 | Deficient Application - Owner Notification Sent |
| Jan 04, 2013 | Deficient Application Picked Up |
| Jan 09, 2013 | Deficiency Response Received |
| Jan 11, 2013 | Team Review for Completeness |
| Jan 11, 2013 | Application Accepted |
| Jan 11, 2013 | Biologist Report |
| Jan 14, 2013 | Typist for Processing |
| Jan 14, 2013 | Executive Sign Off |
| Jan 14, 2013 | Sent to Photo Copy |
| Jan 14, 2013 | Permit Approved |
| Mar 27, 2013 | Land Evidence Date |
| May 01, 2013 | Additional Information Received |