| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| May 14, 2013 | Assent Application Received |
| May 21, 2013 | Application Accepted |
| May 30, 2013 | HPHC Historical Preservation No Effect |
| Jul 08, 2013 | 30 day Public Notice Issued |
| Aug 08, 2013 | Public Notice End Date |
| Aug 08, 2013 | Typist for Processing |
| Aug 08, 2013 | Permit Approved |
| Aug 08, 2013 | Policy Review |
| Aug 09, 2013 | Executive Sign Off |
| Aug 09, 2013 | Sent to Photo Copy |
| Aug 20, 2013 | Land Evidence Date |
| Aug 28, 2013 | Monitoring Report |
| Aug 28, 2013 | Site Inspection |
| Aug 28, 2013 | Commencement of Work Notice received |
| Aug 28, 2013 | Site Inspection |
| Dec 13, 2013 | Monitoring Report |
| Feb 21, 2014 | Monitoring Report |
| Oct 24, 2014 | Monitoring Report |
| Sep 18, 2015 | Monitoring Report |
| Jan 11, 2019 | Monitoring Report |