| Action Date | Action Description | 
|---|---|
| Oct 06, 2014 | Assent Application Received | 
| Oct 06, 2014 | Administrative Review for Completeness | 
| Oct 08, 2014 | Team Review for Completeness | 
| Oct 08, 2014 | Team Review for Completeness | 
| Oct 08, 2014 | Application Accepted | 
| Oct 22, 2014 | 30 day Public Notice Issued | 
| Nov 07, 2014 | HPHC Historical Preservation No Effect | 
| Nov 22, 2014 | Public Notice End Date | 
| Nov 24, 2014 | US Army Corps of Engineers Approval Received | 
| Jan 22, 2015 | Plans Received | 
| Feb 06, 2015 | Dock Meeting Scheduled (Admin) | 
| Feb 18, 2015 | Dock Meeting -- Approval | 
| Feb 23, 2015 | Engineering Report | 
| Feb 23, 2015 | Biologist Report | 
| Feb 24, 2015 | Typist for Processing | 
| Feb 26, 2015 | Executive Sign Off | 
| Feb 26, 2015 | Sent to Photo Copy | 
| Feb 26, 2015 | Permit Approved | 
| Mar 24, 2015 | Land Evidence Date |