| Action Date | Action Description | 
|---|---|
| Nov 20, 2014 | Assent Application Received | 
| Dec 01, 2014 | Team Review for Completeness | 
| Dec 08, 2014 | Deficient Application - Owner Notification Sent | 
| Dec 24, 2014 | Deficiency Response Received | 
| Dec 31, 2014 | Team Review for Completeness | 
| Dec 31, 2014 | Application Accepted | 
| Feb 06, 2015 | HPHC Historical Preservation No Effect | 
| Feb 17, 2015 | Correspondence Received | 
| Mar 04, 2015 | Correspondence Received | 
| Mar 06, 2015 | Biologist Report | 
| Mar 09, 2015 | Permit Approved | 
| Mar 10, 2015 | Typist for Processing | 
| Mar 10, 2015 | Executive Sign Off | 
| Mar 10, 2015 | Sent to Photo Copy | 
| Jun 24, 2015 | Land Evidence Date |