| Action Date | Action Description | 
|---|---|
| Sep 29, 2015 | Assent Application Received | 
| Sep 30, 2015 | Administrative Review for Completeness | 
| Oct 01, 2015 | Team Review for Completeness | 
| Oct 01, 2015 | Application Accepted | 
| Oct 01, 2015 | Category B assigned | 
| Oct 16, 2015 | 30 day Public Notice Issued | 
| Oct 29, 2015 | Biologist Report | 
| Oct 29, 2015 | Stipulation Package from Biologist | 
| Oct 30, 2015 | Stipulation Package by Engineer | 
| Oct 30, 2015 | Engineering Report | 
| Oct 31, 2015 | Public Notice End Date | 
| Nov 02, 2015 | Executive Signoff of Staff Reports | 
| Nov 02, 2015 | Mail Agenda Notice | 
| Nov 03, 2015 | HPHC Historical Preservation No Effect | 
| Nov 10, 2015 | Semi-Monthly Meeting Date Scheduled | 
| Nov 16, 2015 | Typist for Processing | 
| Nov 18, 2015 | Executive Sign Off | 
| Nov 18, 2015 | Sent to Photo Copy | 
| Nov 18, 2015 | Permit Approved | 
| Dec 08, 2015 | Land Evidence Date |