| Action Date | Action Description | 
|---|---|
| Dec 22, 2015 | Freshwater Wetland - Preliminary Determination | 
| Dec 22, 2015 | Administrative Review for Completeness | 
| Dec 28, 2015 | Team Review for Completeness | 
| Dec 28, 2015 | Team Review for Completeness | 
| Dec 28, 2015 | Application Accepted | 
| Feb 01, 2016 | Additional Information Requested from Applicant | 
| Feb 02, 2016 | HPHC Historical Preservation No Effect | 
| Feb 23, 2016 | Plans Received | 
| Mar 21, 2016 | Plans Received | 
| Mar 25, 2016 | Biologist Report | 
| Mar 25, 2016 | Engineering Report | 
| Mar 29, 2016 | Typist for Processing | 
| Mar 30, 2016 | Executive Sign Off | 
| Mar 30, 2016 | Sent to Photo Copy | 
| Mar 30, 2016 | Permit Approved | 
| Apr 06, 2016 | Land Evidence Date |