| Action Date | Action Description | 
|---|---|
| Feb 16, 2016 | Assent Application Received | 
| Feb 16, 2016 | Administrative Review for Completeness | 
| Feb 18, 2016 | Team Review for Completeness | 
| Feb 18, 2016 | Application Accepted | 
| Feb 22, 2016 | Additional Information Received | 
| Apr 07, 2016 | HPHC Historical Preservation Comments/Concerns | 
| Aug 22, 2016 | Correspondence Received | 
| Aug 26, 2016 | Biologist Report | 
| Aug 26, 2016 | Engineering Report | 
| Aug 30, 2016 | Typist for Processing | 
| Aug 31, 2016 | Executive Sign Off | 
| Aug 31, 2016 | Sent to Photo Copy | 
| Aug 31, 2016 | Permit Approved |