| Action Date | Action Description | 
|---|---|
| Mar 17, 2016 | Assent Application Received | 
| Mar 22, 2016 | Administrative Review for Completeness | 
| Mar 23, 2016 | Team Review for Completeness | 
| Mar 23, 2016 | Application Accepted | 
| Mar 29, 2016 | Engineering Report | 
| Mar 29, 2016 | Typist for Processing | 
| Mar 31, 2016 | Executive Sign Off | 
| Mar 31, 2016 | Sent to Photo Copy | 
| Mar 31, 2016 | Permit Approved | 
| May 03, 2016 | HPHC Historical Preservation No Effect | 
| Mar 20, 2017 | Correspondence Mailed/Faxed/E-mailed |