| Action Date | Action Description | 
|---|---|
| Aug 23, 2016 | Assent Application Received | 
| Aug 24, 2016 | Administrative Review for Completeness | 
| Aug 26, 2016 | Team Review for Completeness | 
| Aug 26, 2016 | Application Accepted | 
| Oct 05, 2016 | HPHC Historical Preservation No Effect | 
| Oct 20, 2016 | Additional Information Requested from Applicant | 
| Jan 19, 2017 | Additional Information Received | 
| Feb 03, 2017 | Plans Received | 
| Feb 07, 2017 | Biologist Report | 
| Feb 08, 2017 | Typist for Processing | 
| Feb 08, 2017 | Executive Sign Off | 
| Feb 08, 2017 | Sent to Photo Copy | 
| Feb 08, 2017 | Permit Approved | 
| Feb 15, 2017 | Land Evidence Date | 
| Apr 18, 2017 | Commencement of Work Notice received | 
| Jul 28, 2017 | Modification Request | 
| Jul 28, 2017 | Administrative Review for Completeness | 
| Aug 23, 2017 | Plans Received | 
| Aug 24, 2017 | Team Review for Completeness | 
| Aug 25, 2017 | Application Accepted | 
| Sep 01, 2017 | Biologist Report | 
| Sep 06, 2017 | Typist for Processing | 
| Sep 06, 2017 | Executive Sign Off | 
| Sep 06, 2017 | Sent to Photo Copy | 
| Sep 06, 2017 | Modification Approved | 
| Sep 07, 2017 | HPHC Historical Preservation No Effect | 
| Sep 11, 2017 | Land Evidence Date | 
| Oct 11, 2019 | Commencement of Work Notice received | 
| Dec 23, 2019 | Extension of Permit Request | 
| Jan 31, 2020 | Enforcement Compliance Inspection Required | 
| Feb 17, 2020 | Extension Approved |