| Action Date | Action Description | 
|---|---|
| Oct 21, 2016 | Assent Application Received | 
| Oct 24, 2016 | Administrative Review for Completeness | 
| Oct 27, 2016 | Additional Information Requested from Applicant | 
| Nov 01, 2016 | Additional Information Requested from Applicant | 
| Nov 01, 2016 | Team Review for Completeness | 
| Nov 10, 2016 | HPHC Historical Preservation No Effect | 
| Dec 05, 2016 | Deficiency Response Received | 
| Dec 12, 2016 | Team Review for Completeness | 
| Dec 12, 2016 | Additional Information Requested from Applicant | 
| Dec 13, 2016 | Application Accepted | 
| Dec 13, 2016 | Plans Received | 
| Dec 15, 2016 | Biologist Report | 
| Dec 19, 2016 | Typist for Processing | 
| Dec 19, 2016 | Executive Sign Off | 
| Dec 19, 2016 | Sent to Photo Copy | 
| Dec 19, 2016 | HPHC Historical Preservation No Effect | 
| Dec 19, 2016 | Permit Approved | 
| Dec 21, 2016 | Land Evidence Date |