| Action Date | Action Description | 
|---|---|
| Jan 17, 2017 | Assent Application Received | 
| Jan 17, 2017 | Administrative Review for Completeness | 
| Jan 18, 2017 | Team Review for Completeness | 
| Jan 18, 2017 | Team Review for Completeness | 
| Jan 18, 2017 | Application Accepted | 
| Jan 27, 2017 | HPHC Historical Preservation No Effect | 
| Feb 01, 2017 | 30 day Public Notice Issued | 
| Feb 27, 2017 | Objections/Comments Received | 
| Mar 02, 2017 | Public Notice End Date | 
| Mar 06, 2017 | Plans Received | 
| Apr 10, 2017 | US Army Corps of Engineers Approval Received | 
| Apr 10, 2017 | Public Hearing Notices Mailed | 
| Apr 17, 2017 | Additional Information Received | 
| May 02, 2017 | Biologist Report | 
| May 02, 2017 | Engineering Report | 
| May 09, 2017 | Semi-Monthly Meeting Date Scheduled | 
| May 09, 2017 | Council Approval Granted | 
| Jul 24, 2017 | Stipulation Package from Biologist | 
| Jul 24, 2017 | Stipulation Package by Engineer | 
| Jul 26, 2017 | Typist for Processing | 
| Jul 26, 2017 | Category B assigned | 
| Jul 26, 2017 | Executive Sign Off | 
| Jul 26, 2017 | Sent to Photo Copy | 
| Jul 26, 2017 | Permit Approved | 
| Mar 05, 2018 | Modification Request | 
| Mar 06, 2018 | Administrative Review for Completeness | 
| Mar 06, 2018 | Team Review for Completeness | 
| Mar 06, 2018 | Application Accepted | 
| Mar 09, 2018 | HPHC Historical Preservation No Effect | 
| May 18, 2018 | Biologist Report | 
| May 18, 2018 | Typist for Processing | 
| May 18, 2018 | Executive Sign Off | 
| May 18, 2018 | Sent to Photo Copy | 
| May 18, 2018 | Modification Approved | 
| Jul 20, 2018 | Duplicate Original Assent requested/mailed | 
| May 15, 2019 | Land Evidence Date | 
| Aug 08, 2019 | Plans Received |