| Action Date | Action Description |
|---|---|
| Aug 15, 2017 | Assent Application Received |
| Aug 15, 2017 | Administrative Review for Completeness |
| Aug 17, 2017 | Team Review for Completeness |
| Aug 17, 2017 | Application Accepted |
| Aug 31, 2017 | HPHC Historical Preservation No Effect |
| Nov 01, 2017 | Biologist Report |
| Nov 02, 2017 | Typist for Processing |
| Nov 02, 2017 | Executive Sign Off |
| Nov 02, 2017 | Sent to Photo Copy |
| Nov 02, 2017 | Permit Approved |
| Mar 07, 2018 | Land Evidence Date |
| May 09, 2018 | Correspondence Received |
| May 17, 2018 | Permit Rescinded |