| Action Date | Action Description | 
|---|---|
| Nov 09, 2017 | Dredge Application | 
| Nov 09, 2017 | Administrative Review for Completeness | 
| Nov 20, 2017 | Team Review for Completeness | 
| Nov 20, 2017 | Application Accepted | 
| Nov 22, 2017 | Additional Information Received | 
| Dec 01, 2017 | 30 day Public Notice Issued | 
| Dec 14, 2017 | Letter of Support for Project | 
| Dec 31, 2017 | Public Notice End Date | 
| Jan 05, 2018 | Typist for Processing | 
| Jan 05, 2018 | Executive Sign Off | 
| Jan 05, 2018 | Permit Approved | 
| Jan 05, 2018 | Engineering Report | 
| Jan 10, 2018 | Land Evidence Date |