| Action Date | Action Description | 
|---|---|
| Nov 14, 2017 | Assent Application Received | 
| Nov 14, 2017 | Administrative Review for Completeness | 
| Nov 15, 2017 | Application Accepted | 
| Nov 17, 2017 | Team Review for Completeness | 
| Nov 28, 2017 | HPHC Historical Preservation No Effect | 
| Jan 17, 2018 | Engineering Report | 
| Jan 17, 2018 | Typist for Processing | 
| Jan 17, 2018 | Executive Sign Off | 
| Jan 17, 2018 | Sent to Photo Copy | 
| Jan 17, 2018 | Permit Approved | 
| Feb 07, 2018 | Land Evidence Date | 
| Oct 15, 2019 | Modification Request | 
| Oct 16, 2019 | Administrative Review for Completeness | 
| Oct 17, 2019 | Eng Team Review for Completeness | 
| Nov 07, 2019 | HPHC Historical Preservation No Effect | 
| Nov 07, 2019 | HPHC Review Pending | 
| Dec 09, 2019 | Typist for Processing | 
| Dec 09, 2019 | Executive Sign Off | 
| Dec 09, 2019 | Sent to Photo Copy | 
| Dec 09, 2019 | Modification Approved | 
| Dec 09, 2019 | Engineering Report | 
| Jan 02, 2020 | Duplicate Original Assent requested/mailed | 
| Jan 14, 2020 | Land Evidence Date |