| Action Date | Action Description | 
|---|---|
| Feb 12, 2018 | Assent Application Received | 
| Feb 12, 2018 | Administrative Review for Completeness | 
| Feb 13, 2018 | Team Review for Completeness | 
| Feb 13, 2018 | Application Accepted | 
| Feb 26, 2018 | HPHC Historical Preservation No Effect | 
| Mar 08, 2018 | Plans Received | 
| Mar 09, 2018 | 30 day Public Notice Issued | 
| Apr 09, 2018 | Public Notice End Date | 
| Apr 17, 2018 | Additional Information Received | 
| Apr 19, 2018 | Executive Signoff of Staff Reports | 
| Apr 19, 2018 | Biologist Report | 
| Apr 19, 2018 | Mail Agenda Notice | 
| May 08, 2018 | Semi-Monthly Meeting Postponed | 
| May 08, 2018 | Semi-Monthly Meeting Date Scheduled | 
| May 08, 2018 | Mail Agenda Notice | 
| May 10, 2018 | Correspondence Mailed/Faxed/E-mailed | 
| May 21, 2018 | Mail Agenda Notice | 
| May 22, 2018 | Semi-Monthly Meeting Postponed | 
| May 22, 2018 | Semi-Monthly Meeting Date Scheduled | 
| Jun 12, 2018 | Semi-Monthly Meeting Date Scheduled | 
| Jun 12, 2018 | US Army Corps of Engineers Approval Received | 
| Jun 12, 2018 | Council Approval Granted | 
| Jul 09, 2018 | Legal Response/Decision | 
| Jul 11, 2018 | Stipulation Package from Biologist | 
| Jul 13, 2018 | Stipulation Package by Engineer | 
| Jul 13, 2018 | Typist for Processing | 
| Jul 13, 2018 | Category B assigned | 
| Jul 13, 2018 | Executive Sign Off | 
| Jul 13, 2018 | Sent to Photo Copy | 
| Jul 13, 2018 | Permit Approved | 
| Jul 20, 2018 | Land Evidence Date | 
| Aug 01, 2019 | Correspondence Received |