| Action Date | Action Description | 
|---|---|
| Apr 11, 2018 | Assent Application Received | 
| Apr 12, 2018 | Administrative Review for Completeness | 
| Apr 19, 2018 | Team Review for Completeness | 
| Apr 23, 2018 | Deficient Application - Owner Notification Sent | 
| Apr 23, 2018 | Team Review for Completeness | 
| May 10, 2018 | Deficient Application Picked Up | 
| Jun 04, 2018 | Deficiency Response Received | 
| Jun 05, 2018 | Team Review for Completeness | 
| Jun 06, 2018 | Team Review for Completeness | 
| Jun 06, 2018 | Application Accepted | 
| Jun 06, 2018 | Category B assigned | 
| Jun 19, 2018 | 30 day Public Notice Issued | 
| Jun 26, 2018 | HPHC Historical Preservation No Effect | 
| Jul 19, 2018 | Public Notice End Date | 
| Sep 21, 2018 | Engineering Report | 
| Sep 24, 2018 | Typist for Processing | 
| Sep 24, 2018 | Executive Sign Off | 
| Sep 24, 2018 | Sent to Photo Copy | 
| Sep 24, 2018 | Permit Approved | 
| Oct 10, 2018 | Land Evidence Date |