| Action Date | Action Description | 
|---|---|
| May 25, 2018 | Freshwater Wetland - Preliminary Determination | 
| May 27, 2018 | Administrative Review for Completeness | 
| May 29, 2018 | Team Review for Completeness | 
| May 29, 2018 | Application Accepted | 
| Jun 12, 2018 | HPHC Historical Preservation No Effect | 
| Aug 07, 2018 | Biologist Report | 
| Aug 09, 2018 | Typist for Processing | 
| Aug 09, 2018 | Executive Sign Off | 
| Aug 09, 2018 | Sent to Photo Copy | 
| Aug 09, 2018 | Permit Approved | 
| Jun 23, 2021 | Extension of Permit Request | 
| Feb 22, 2022 | Extension Approved | 
| May 31, 2022 | Correspondence Received | 
| Jun 21, 2022 | Correspondence Received | 
| Jun 21, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Jun 22, 2022 | Correspondence Received | 
| Jun 22, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Aug 08, 2022 | Monitoring Report | 
| Oct 25, 2022 | Monitoring Report |