| Action Date | Action Description | 
|---|---|
| Sep 13, 2018 | Freshwater Wetland - Preliminary Determination | 
| Sep 13, 2018 | Administrative Review for Completeness | 
| Sep 17, 2018 | Team Review for Completeness | 
| Sep 17, 2018 | Application Accepted | 
| Oct 02, 2018 | HPHC Historical Preservation No Effect | 
| Oct 30, 2018 | Additional Information Requested from Applicant | 
| Nov 05, 2018 | Additional Information Received | 
| Nov 14, 2018 | Biologist Report | 
| Nov 16, 2018 | Typist for Processing | 
| Nov 16, 2018 | Executive Sign Off | 
| Nov 16, 2018 | Sent to Photo Copy | 
| Nov 16, 2018 | Permit Approved | 
| Jan 31, 2019 | Land Evidence Date | 
| Apr 09, 2020 | Modification Request | 
| Apr 09, 2020 | Administrative Review for Completeness | 
| Apr 20, 2020 | Bio Team Review for Completeness | 
| Apr 20, 2020 | Project Manager | 
| Apr 20, 2020 | Additional Information Received | 
| Apr 27, 2020 | HPHC Review Pending | 
| Apr 27, 2020 | HPHC Historical Preservation No Effect | 
| May 20, 2020 | Biologist Report | 
| May 21, 2020 | Typist for Processing | 
| May 21, 2020 | Executive Sign Off | 
| May 21, 2020 | Sent to Photo Copy | 
| May 21, 2020 | Modification Approved | 
| Jun 01, 2020 | Land Evidence Date | 
| Oct 15, 2021 | Modification Request | 
| Oct 19, 2021 | Administrative Review for Completeness | 
| Oct 20, 2021 | Bio Team Review for Completeness | 
| Oct 26, 2021 | HPHC Historical Preservation No Effect | 
| Oct 26, 2021 | HPHC Review Pending | 
| Nov 19, 2021 | Typist for Processing | 
| Nov 19, 2021 | Executive Sign Off | 
| Nov 19, 2021 | Sent to Photo Copy | 
| Nov 19, 2021 | Biologist Report | 
| Nov 19, 2021 | Modification Approved | 
| Dec 01, 2021 | Permit Mailed | 
| Jan 18, 2022 | Land Evidence Date |