| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 26, 2018 | Assent Application Received | 
| Dec 26, 2018 | Administrative Review for Completeness | 
| Dec 27, 2018 | Team Review for Completeness | 
| Dec 27, 2018 | Application Accepted | 
| Jan 02, 2019 | 30 day Public Notice Issued | 
| Jan 16, 2019 | HPHC Historical Preservation No Effect | 
| Jan 16, 2019 | HPHC Review Pending | 
| Jan 23, 2019 | Comments Received | 
| Feb 02, 2019 | Public Notice End Date | 
| Apr 25, 2019 | Additional Information Received | 
| Apr 30, 2019 | Additional Information Received | 
| May 02, 2019 | Dock Meeting -- Approval | 
| May 08, 2019 | Biologist Report | 
| May 10, 2019 | Typist for Processing | 
| May 10, 2019 | Executive Sign Off | 
| May 10, 2019 | Sent to Photo Copy | 
| May 10, 2019 | Permit Approved | 
| May 20, 2019 | Land Evidence Date | 
| Nov 05, 2019 | Correspondence Mailed/Faxed/E-mailed | 
| Nov 05, 2019 | Correspondence Mailed/Faxed/E-mailed | 
| Nov 06, 2019 | Permit Rescinded | 
| Nov 09, 2019 | Certified Receipt Received | 
| May 19, 2020 | Note to File | 
| May 19, 2020 | Permit Approved | 
| Nov 27, 2023 | Land Evidence Date | 
| Dec 07, 2023 | Correspondence Received |