| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 31, 2018 | Assent Application Received | 
| Dec 31, 2018 | Administrative Review for Completeness | 
| Jan 09, 2019 | Team Review for Completeness | 
| Jan 09, 2019 | Deficient Application - Owner Notification Sent | 
| Jan 23, 2019 | Deficient Application Picked Up | 
| Apr 29, 2019 | Deficiency Response Received | 
| Apr 30, 2019 | Team Review for Completeness | 
| Apr 30, 2019 | Application Accepted | 
| May 10, 2019 | HPHC Review Pending | 
| May 10, 2019 | HPHC Historical Preservation No Effect | 
| May 28, 2019 | 30 day Public Notice Issued | 
| Jun 28, 2019 | Public Notice End Date | 
| Aug 02, 2019 | Dock/1.1.6 Review approval | 
| Sep 17, 2019 | Typist for Processing | 
| Sep 17, 2019 | Executive Sign Off | 
| Sep 17, 2019 | Sent to Photo Copy | 
| Sep 17, 2019 | Permit Approved | 
| Sep 17, 2019 | Biologist Report | 
| Sep 17, 2019 | Engineering Report | 
| Oct 02, 2019 | Land Evidence Date | 
| Jun 03, 2024 | Modification Request | 
| Jun 10, 2024 | Administrative Review for Completeness | 
| Jun 12, 2024 | Bio Team Review for Completeness | 
| Jun 26, 2024 | Deficient Application - Owner Notification Sent | 
| Jun 26, 2024 | Eng Team Review for Completeness | 
| Jul 05, 2024 | Deficiency Response Received | 
| Nov 08, 2024 | Eng Team Review for Completeness | 
| Nov 08, 2024 | Application Accepted | 
| Nov 19, 2024 | HPHC Historical Preservation No Effect | 
| Nov 29, 2024 | 30 day Public Notice Issued | 
| Dec 29, 2024 | Public Notice End Date | 
| Feb 28, 2025 | Typist for Processing | 
| Feb 28, 2025 | Executive Sign Off | 
| Feb 28, 2025 | Sent to Photo Copy | 
| Feb 28, 2025 | Modification Approved | 
| Feb 28, 2025 | Modification mailed | 
| Feb 28, 2025 | Engineering Report | 
| Mar 06, 2025 | Permit Mailed | 
| Oct 30, 2025 | Land Evidence Date |