| Action Date | Action Description | 
|---|---|
| Legal Response/Decision | |
| Dock Post-Construction Certification by Engineer received. | |
| Mar 05, 2019 | Assent Application Received | 
| Mar 11, 2019 | Administrative Review for Completeness | 
| Mar 11, 2019 | Team Review for Completeness | 
| Mar 11, 2019 | Application Accepted | 
| Mar 20, 2019 | HPHC Historical Preservation No Effect | 
| Mar 20, 2019 | HPHC Review Pending | 
| Apr 16, 2019 | Additional Information Received | 
| Jul 10, 2019 | Additional Information Received | 
| Aug 19, 2019 | Additional Information Received | 
| Aug 27, 2019 | Plans Received | 
| Aug 29, 2019 | Water Quality Certification | 
| Sep 06, 2019 | 30 day Public Notice Issued | 
| Oct 06, 2019 | Public Notice End Date | 
| Oct 07, 2019 | Biologist Report | 
| Oct 09, 2019 | Engineering Report | 
| Oct 09, 2019 | Mail Agenda Notice | 
| Oct 11, 2019 | Executive Signoff of Staff Reports | 
| Oct 22, 2019 | Council Approval Granted | 
| Oct 22, 2019 | Semi-Monthly Meeting Date Scheduled | 
| Dec 03, 2019 | Stipulation Package by Engineer | 
| Dec 16, 2019 | Typist for Processing | 
| Dec 16, 2019 | Executive Sign Off | 
| Dec 16, 2019 | Sent to Photo Copy | 
| Dec 16, 2019 | Permit Approved | 
| Dec 16, 2019 | Stipulation Package from Biologist | 
| Mar 10, 2020 | Land Evidence Date |