| Action Date | Action Description | 
|---|---|
| Team Review for Completeness | |
| Jul 11, 2019 | Assent Application Received | 
| Jul 11, 2019 | Administrative Review for Completeness | 
| Jul 23, 2019 | Application Accepted | 
| Jul 23, 2019 | Team Review for Completeness | 
| Aug 22, 2019 | HPHC Review Pending | 
| Aug 22, 2019 | HPHC Historical Preservation No Effect | 
| Aug 29, 2019 | Typist for Processing | 
| Aug 29, 2019 | Executive Sign Off | 
| Aug 29, 2019 | Sent to Photo Copy | 
| Aug 29, 2019 | Permit Approved | 
| Aug 29, 2019 | Engineering Report | 
| Oct 28, 2019 | Modification Request | 
| Oct 29, 2019 | Administrative Review for Completeness | 
| Nov 04, 2019 | Eng Team Review for Completeness | 
| Nov 07, 2019 | HPHC Review Pending | 
| Nov 07, 2019 | HPHC Historical Preservation No Effect | 
| Nov 15, 2019 | Typist for Processing | 
| Nov 15, 2019 | Modification Approved | 
| Nov 15, 2019 | Engineering Report | 
| Jan 09, 2020 | Land Evidence Date | 
| Apr 06, 2020 | Commencement of Work Notice received |