| Action Date | Action Description | 
|---|---|
| Aug 05, 2019 | Assent Application Received | 
| Aug 05, 2019 | Administrative Review for Completeness | 
| Aug 08, 2019 | Team Review for Completeness | 
| Aug 08, 2019 | Application Accepted | 
| Sep 13, 2019 | Plans Received | 
| Sep 17, 2019 | Joint Public Notice | 
| Sep 20, 2019 | HPHC Review Pending | 
| Sep 20, 2019 | HPHC Historical Preservation No Effect | 
| Oct 17, 2019 | Public Notice End Date | 
| Jan 08, 2020 | Additional Information Received | 
| Jan 22, 2020 | Plans Received | 
| Feb 13, 2020 | Mail Agenda Notice | 
| Feb 14, 2020 | Biologist Report | 
| Feb 14, 2020 | Engineering Report | 
| Feb 18, 2020 | Additional Information Received | 
| Feb 25, 2020 | Council Approval Granted | 
| Feb 25, 2020 | Semi-Monthly Meeting Date Scheduled | 
| Mar 06, 2020 | Additional Information Received | 
| Mar 20, 2020 | Stipulation Package from Biologist | 
| Mar 24, 2020 | Stipulation Package by Engineer | 
| Mar 24, 2020 | Typist for Processing | 
| Mar 24, 2020 | Executive Sign Off | 
| Mar 24, 2020 | Sent to Photo Copy | 
| Mar 24, 2020 | Assent Requirement | 
| Mar 24, 2020 | Permit Approved | 
| Aug 24, 2020 | Land Evidence Date | 
| Dec 14, 2021 | Additional Information Received | 
| Jan 13, 2022 | Modification Request | 
| Jan 14, 2022 | Administrative Review for Completeness | 
| Jan 14, 2022 | Eng Team Review for Completeness | 
| Jan 14, 2022 | Project Manager | 
| Jan 14, 2022 | Engineering Report | 
| Jan 14, 2022 | Typist for Processing | 
| Jan 14, 2022 | Modification Approved | 
| Jan 18, 2022 | Permit Mailed | 
| Jan 20, 2022 | Additional Information Received | 
| Jan 24, 2022 | Additional Information Received | 
| Jan 20, 2023 | Extension of Permit Request | 
| Jan 25, 2023 | Additional Information Received | 
| Feb 20, 2023 | Extension Approved | 
| Sep 13, 2023 | Correspondence Received |