| Action Date | Action Description |
|---|---|
| Sep 06, 2019 | Assent Application Received |
| Sep 06, 2019 | Administrative Review for Completeness |
| Sep 09, 2019 | Team Review for Completeness |
| Sep 09, 2019 | Deficiency - Phone Call to Applicant/Owner |
| Sep 11, 2019 | Deficiency Response Received |
| Sep 16, 2019 | Team Review for Completeness |
| Sep 16, 2019 | Application Accepted |
| Sep 20, 2019 | Plans Received |
| Sep 25, 2019 | Plans Received |
| Sep 27, 2019 | Biologist Report |
| Oct 04, 2019 | HPHC Review Pending |
| Oct 04, 2019 | HPHC Historical Preservation No Effect |
| Oct 08, 2019 | Typist for Processing |
| Oct 08, 2019 | Executive Sign Off |
| Oct 08, 2019 | Sent to Photo Copy |
| Oct 08, 2019 | Permit Approved |
| Dec 10, 2019 | Land Evidence Date |