| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 29, 2020 | Assent Application Received |
| Jan 30, 2020 | Administrative Review for Completeness |
| Jan 30, 2020 | Eng Team Review for Completeness |
| Jan 30, 2020 | Bio Team Review for Completeness |
| Jan 30, 2020 | Application Accepted |
| Feb 25, 2020 | HPHC Historical Preservation No Effect |
| Feb 25, 2020 | HPHC Review Pending |
| Mar 02, 2020 | Additional Information Received |
| Mar 20, 2020 | Plans Received |
| Mar 23, 2020 | Joint Public Notice |
| Apr 23, 2020 | Public Notice End Date |
| May 06, 2020 | Water Quality Certification |
| May 14, 2020 | Executive Signoff of Staff Reports |
| May 14, 2020 | Biologist Report |
| May 14, 2020 | Engineering Report |
| May 15, 2020 | Mail Agenda Notice |
| May 26, 2020 | Semi-Monthly Meeting Date Scheduled |
| May 29, 2020 | Typist for Processing |
| May 29, 2020 | Executive Sign Off |
| May 29, 2020 | Sent to Photo Copy |
| May 29, 2020 | Permit Approved |
| Jun 03, 2020 | Land Evidence Date |